Original Cost
₹320 Cr
Baseline estimate
Revised Cost
₹320 Cr
Latest approved cost
Expenditure
₹197 Cr
Spent to date
Utilization
61.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹123 Cr
Budget left
Spent
₹197 Cr
Remaining
₹123 Cr
Total
₹320 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹320 Cr — no cost escalation recorded.
Expenditure stands at ₹197 Cr, which is 61.5% of the revised project cost.
Remaining budget: ₹123 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.