New Sinter Plant at BSL, SAIL

Ministry of SteelJharkhand
Revised Cost: ₹1752 CrUtilization: 61.4%Overrun: +₹718 Cr

Original Cost

₹1034 Cr

Baseline estimate

+70% overrun

Revised Cost

₹1752 Cr

Latest approved cost

Expenditure

₹1075 Cr

Spent to date

Utilization

61.4%

Of revised budget

Escalated

Cost Status

+69.5%

+₹718 Cr increase

Remaining

₹677 Cr

Budget left

Budget Utilization

61.4%
0%25%50%75%100%

Spent

₹1075 Cr

Remaining

₹677 Cr

Total

₹1752 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1034 Cr

Revised Cost

₹1752 Cr

Increase

+₹718 Cr

Escalation

+69.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/10/2027

Revised Completion

30/06/2027

Completed

Project Details

Project Code400174
SectorSteel
MinistryMinistry of Steel
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹1034 Cr
Revised Cost₹1752 Cr
Expenditure₹1075 Cr
Original End Date31/10/2027
Revised Date30/06/2027

Project Intelligence

Cost has increased by ₹718 Cr (69.5%) from the original estimate of ₹1034 Cr.

Expenditure stands at ₹1075 Cr, which is 61.4% of the revised project cost.

Remaining budget: ₹677 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

New Sinter Plant at BSL, SAIL is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹1034.00 Cr, later revised to ₹1752.30 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "New Sinter Plant at BSL, SAIL"?
New Sinter Plant at BSL, SAIL is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Jharkhand. Original cost: ₹1034 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1034 Cr and has been revised to ₹1752 Cr — a cost overrun of +69.5%. Expenditure to date: ₹1075 Cr (61.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
New Sinter Plant at BSL, SAIL is under the Ministry of Steel in the Steel sector. Project code: 400174. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. New Sinter Plant at BSL, SAIL is one of several Bihar projects tracked under the Steel sector on the IPM system.