Original Cost
₹1034 Cr
Baseline estimate
Revised Cost
₹1752 Cr
Latest approved cost
Expenditure
₹1007 Cr
Spent to date
Utilization
57.4%
Of revised budget
Cost Status
+69.5%
+₹718 Cr increase
Remaining
₹746 Cr
Budget left
Spent
₹1007 Cr
Remaining
₹746 Cr
Total
₹1752 Cr
Original Cost
₹1034 Cr
Revised Cost
₹1752 Cr
Increase
+₹718 Cr
Escalation
+69.5%
Project Approved
Construction / Implementation
Original End Date
31/10/2017
Revised Completion
30/06/2027
Completed
Cost has increased by ₹718 Cr (69.5%) from the original estimate of ₹1034 Cr.
Expenditure stands at ₹1007 Cr, which is 57.4% of the revised project cost.
Remaining budget: ₹746 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.