Original Cost
₹1025 Cr
Baseline estimate
Revised Cost
₹1025 Cr
Latest approved cost
Expenditure
₹217 Cr
Spent to date
Utilization
21.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹808 Cr
Budget left
Spent
₹217 Cr
Remaining
₹808 Cr
Total
₹1025 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2029
Revised Completion
Completed
Project is within original budget of ₹1025 Cr — no cost escalation recorded.
Expenditure stands at ₹217 Cr, which is 21.2% of the revised project cost.
Remaining budget: ₹808 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.