Original Cost
₹23.1K Cr
Baseline estimate
Revised Cost
₹37.3K Cr
Latest approved cost
Expenditure
₹33.6K Cr
Spent to date
Utilization
90.3%
Of revised budget
Cost Status
+61.1%
+₹14.1K Cr increase
Remaining
₹3628 Cr
Budget left
Spent
₹33.6K Cr
Remaining
₹3628 Cr
Total
₹37.3K Cr
Original Cost
₹23.1K Cr
Revised Cost
₹37.3K Cr
Increase
+₹14.1K Cr
Escalation
+61.1%
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
31/08/2025
Completed
Mega infrastructure project worth ₹37.3K Cr — among the largest central projects in Maharashtra.
Cost has increased by ₹14.1K Cr (61.1%) from the original estimate of ₹23.1K Cr.
Expenditure stands at ₹33.6K Cr, which is 90.3% of the revised project cost.
Remaining budget: ₹3628 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.