Electricity GenerationIPM · Central Project#298178

Meja Thermal Power Project, Stage-II , (3x800 MW)

Ministry of PowerUttar Pradesh
Revised Cost: ₹38.4K CrUtilization: 2.7%

Original Cost

₹38.4K Cr

Baseline estimate

On budget

Revised Cost

₹38.4K Cr

Latest approved cost

Expenditure

₹1028 Cr

Spent to date

Utilization

2.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹37.3K Cr

Budget left

Budget Utilization

2.7%
0%25%50%75%100%

Spent

₹1028 Cr

Remaining

₹37.3K Cr

Total

₹38.4K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2032

Revised Completion

Completed

Project Details

Project Code298178
SectorElectricity Generation
MinistryMinistry of Power
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹38.4K Cr
Revised Cost₹38.4K Cr
Expenditure₹1028 Cr
Original End Date31/12/2032
Revised DateN/A

Project Intelligence

Mega infrastructure project worth ₹38.4K Cr — among the largest central projects in Uttar Pradesh.

Project is within original budget of ₹38.4K Cr — no cost escalation recorded.

Expenditure stands at ₹1028 Cr, which is 2.7% of the revised project cost.

Remaining budget: ₹37.3K Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Meja Thermal Power Project, Stage-II , (3x800 MW) is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹38358.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Meja Thermal Power Project, Stage-II , (3x800 MW)"?
Meja Thermal Power Project, Stage-II , (3x800 MW) is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Uttar Pradesh. Original cost: ₹38358 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹38358 Cr has not been significantly revised. Expenditure: ₹1028 Cr (2.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Meja Thermal Power Project, Stage-II , (3x800 MW) is under the Ministry of Power in the Electricity Generation sector. Project code: 298178. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Meja Thermal Power Project, Stage-II , (3x800 MW) is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.