Luhri Stage-I Hydro Electric Project [210 MW]
Original Cost
₹1811 Cr
Baseline estimate
Revised Cost
₹4345 Cr
Latest approved cost
Expenditure
₹1981 Cr
Spent to date
Utilization
45.6%
Of revised budget
Cost Status
+139.9%
+₹2534 Cr increase
Remaining
₹2364 Cr
Budget left
Budget Utilization
45.6%Spent
₹1981 Cr
Remaining
₹2364 Cr
Total
₹4345 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1811 Cr
Revised Cost
₹4345 Cr
Increase
+₹2534 Cr
Escalation
+139.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/01/2026
Revised Completion
29/05/2030
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹2534 Cr (139.9%) from the original estimate of ₹1811 Cr.
Expenditure stands at ₹1981 Cr, which is 45.6% of the revised project cost.
Remaining budget: ₹2364 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Luhri Stage-I Hydro Electric Project [210 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹1811.00 Cr, later revised to ₹4345.31 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Luhri Stage-I Hydro Electric Project [210 MW]"?
- Luhri Stage-I Hydro Electric Project [210 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Himachal Pradesh. Original cost: ₹1811 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1811 Cr and has been revised to ₹4345 Cr — a cost overrun of +139.9%. Expenditure to date: ₹1981 Cr (45.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Luhri Stage-I Hydro Electric Project [210 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602593. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Luhri Stage-I Hydro Electric Project [210 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.