CoalIPM · Central Project#400147

KUSMUNDA OC EXPANSION [15 TO 50 MTY]

Ministry of CoalChhattisgarh
Revised Cost: ₹7612 CrUtilization: 61.7%

Original Cost

₹7612 Cr

Baseline estimate

On budget

Revised Cost

₹7612 Cr

Latest approved cost

Expenditure

₹4698 Cr

Spent to date

Utilization

61.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹2914 Cr

Budget left

Budget Utilization

61.7%
0%25%50%75%100%

Spent

₹4698 Cr

Remaining

₹2914 Cr

Total

₹7612 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2023

Revised Completion

31/03/2030

Completed

Project Details

Project Code400147
SectorCoal
MinistryMinistry of Coal
StateChhattisgarh
Data Month2025-09

Financial Summary

Original Cost₹7612 Cr
Revised Cost₹7612 Cr
Expenditure₹4698 Cr
Original End Date31/03/2023
Revised Date31/03/2030

Project Intelligence

Project is within original budget of ₹7612 Cr — no cost escalation recorded.

Expenditure stands at ₹4698 Cr, which is 61.7% of the revised project cost.

Remaining budget: ₹2914 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

KUSMUNDA OC EXPANSION [15 TO 50 MTY] is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹7612.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "KUSMUNDA OC EXPANSION [15 TO 50 MTY]"?
KUSMUNDA OC EXPANSION [15 TO 50 MTY] is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Chhattisgarh. Original cost: ₹7612 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹7612 Cr has not been significantly revised. Expenditure: ₹4698 Cr (61.7% of cost). Data as of 2025-09.
QWhich ministry is responsible for this project?
KUSMUNDA OC EXPANSION [15 TO 50 MTY] is under the Ministry of Coal in the Coal sector. Project code: 400147. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. KUSMUNDA OC EXPANSION [15 TO 50 MTY] is one of several Bihar projects tracked under the Coal sector on the IPM system.