Original Cost
₹675 Cr
Baseline estimate
Revised Cost
₹675 Cr
Latest approved cost
Expenditure
₹434 Cr
Spent to date
Utilization
64.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹241 Cr
Budget left
Spent
₹434 Cr
Remaining
₹241 Cr
Total
₹675 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2032
Revised Completion
Completed
Project is within original budget of ₹675 Cr — no cost escalation recorded.
Expenditure stands at ₹434 Cr, which is 64.2% of the revised project cost.
Remaining budget: ₹241 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.