Kiru HE Project
Original Cost
₹4288 Cr
Baseline estimate
Revised Cost
₹5409 Cr
Latest approved cost
Expenditure
₹4118 Cr
Spent to date
Utilization
76.1%
Of revised budget
Cost Status
+26.1%
+₹1121 Cr increase
Remaining
₹1291 Cr
Budget left
Budget Utilization
76.1%Spent
₹4118 Cr
Remaining
₹1291 Cr
Total
₹5409 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹4288 Cr
Revised Cost
₹5409 Cr
Increase
+₹1121 Cr
Escalation
+26.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/09/2023
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1121 Cr (26.1%) from the original estimate of ₹4288 Cr.
Expenditure stands at ₹4118 Cr, which is 76.1% of the revised project cost.
Remaining budget: ₹1291 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Kiru HE Project is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹4288.00 Cr, later revised to ₹5409.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Kiru HE Project"?
- Kiru HE Project is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Jammu & Kashmir. Original cost: ₹4288 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹4288 Cr and has been revised to ₹5409 Cr — a cost overrun of +26.1%. Expenditure to date: ₹4118 Cr (76.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Kiru HE Project is under the Ministry of Power in the Electricity Generation sector. Project code: 602532. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kiru HE Project is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.