Electricity GenerationIPM · Central Project +26.1% overrun#602532

Kiru HE Project

Ministry of PowerJammu & Kashmir
Revised Cost: ₹5409 CrUtilization: 76.1%Overrun: +₹1121 Cr

Original Cost

₹4288 Cr

Baseline estimate

+26% overrun

Revised Cost

₹5409 Cr

Latest approved cost

Expenditure

₹4118 Cr

Spent to date

Utilization

76.1%

Of revised budget

Escalated

Cost Status

+26.1%

+₹1121 Cr increase

Remaining

₹1291 Cr

Budget left

Budget Utilization

76.1%
0%25%50%75%100%

Spent

₹4118 Cr

Remaining

₹1291 Cr

Total

₹5409 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹4288 Cr

Revised Cost

₹5409 Cr

Increase

+₹1121 Cr

Escalation

+26.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/09/2023

Revised Completion

31/12/2026

Completed

Project Details

Project Code602532
SectorElectricity Generation
MinistryMinistry of Power
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹4288 Cr
Revised Cost₹5409 Cr
Expenditure₹4118 Cr
Original End Date07/09/2023
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹1121 Cr (26.1%) from the original estimate of ₹4288 Cr.

Expenditure stands at ₹4118 Cr, which is 76.1% of the revised project cost.

Remaining budget: ₹1291 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Kiru HE Project is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹4288.00 Cr, later revised to ₹5409.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kiru HE Project"?
Kiru HE Project is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Jammu & Kashmir. Original cost: ₹4288 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹4288 Cr and has been revised to ₹5409 Cr — a cost overrun of +26.1%. Expenditure to date: ₹4118 Cr (76.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kiru HE Project is under the Ministry of Power in the Electricity Generation sector. Project code: 602532. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kiru HE Project is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.