Original Cost
₹4288 Cr
Baseline estimate
Revised Cost
₹5409 Cr
Latest approved cost
Expenditure
₹3869 Cr
Spent to date
Utilization
71.5%
Of revised budget
Cost Status
+26.1%
+₹1121 Cr increase
Remaining
₹1540 Cr
Budget left
Spent
₹3869 Cr
Remaining
₹1540 Cr
Total
₹5409 Cr
Original Cost
₹4288 Cr
Revised Cost
₹5409 Cr
Increase
+₹1121 Cr
Escalation
+26.1%
Project Approved
Construction / Implementation
Original End Date
07/09/2023
Revised Completion
31/12/2026
Completed
Cost has increased by ₹1121 Cr (26.1%) from the original estimate of ₹4288 Cr.
Expenditure stands at ₹3869 Cr, which is 71.5% of the revised project cost.
Remaining budget: ₹1540 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.