Original Cost
₹492 Cr
Baseline estimate
Revised Cost
₹492 Cr
Latest approved cost
Expenditure
₹276 Cr
Spent to date
Utilization
56.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹216 Cr
Budget left
Spent
₹276 Cr
Remaining
₹216 Cr
Total
₹492 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹492 Cr — no cost escalation recorded.
Expenditure stands at ₹276 Cr, which is 56.2% of the revised project cost.
Remaining budget: ₹216 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.