Original Cost
₹11.1K Cr
Baseline estimate
Revised Cost
₹11.1K Cr
Latest approved cost
Expenditure
₹9099 Cr
Spent to date
Utilization
82.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1977 Cr
Budget left
Spent
₹9099 Cr
Remaining
₹1977 Cr
Total
₹11.1K Cr
Project Approved
Construction / Implementation
Original End Date
26/05/2024
Revised Completion
31/03/2027
Completed
Mega infrastructure project worth ₹11.1K Cr — among the largest central projects in Uttar Pradesh.
Project is within original budget of ₹11.1K Cr — no cost escalation recorded.
Expenditure stands at ₹9099 Cr, which is 82.1% of the revised project cost.
Remaining budget: ₹1977 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.