Original Cost
₹14.1K Cr
Baseline estimate
Revised Cost
₹14.1K Cr
Latest approved cost
Expenditure
₹188 Cr
Spent to date
Utilization
1.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹13.9K Cr
Budget left
Spent
₹188 Cr
Remaining
₹13.9K Cr
Total
₹14.1K Cr
Project Approved
Construction / Implementation
Original End Date
22/10/2032
Revised Completion
Completed
Mega infrastructure project worth ₹14.1K Cr — among the largest central projects in Arunachal Pradesh.
Project is within original budget of ₹14.1K Cr — no cost escalation recorded.
Expenditure stands at ₹188 Cr, which is 1.3% of the revised project cost.
Remaining budget: ₹13.9K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.