Original Cost
₹442 Cr
Baseline estimate
Revised Cost
₹442 Cr
Latest approved cost
Expenditure
₹253 Cr
Spent to date
Utilization
57.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹189 Cr
Budget left
Spent
₹253 Cr
Remaining
₹189 Cr
Total
₹442 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹442 Cr — no cost escalation recorded.
Expenditure stands at ₹253 Cr, which is 57.3% of the revised project cost.
Remaining budget: ₹189 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.