Original Cost
₹279 Cr
Baseline estimate
Revised Cost
₹279 Cr
Latest approved cost
Expenditure
₹210 Cr
Spent to date
Utilization
75.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹69 Cr
Budget left
Spent
₹210 Cr
Remaining
₹69 Cr
Total
₹279 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
30/06/2025
Completed
Project is within original budget of ₹279 Cr — no cost escalation recorded.
Expenditure stands at ₹210 Cr, which is 75.3% of the revised project cost.
Remaining budget: ₹69 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.