Waste & WaterIPM · Central Project#616600

Interception and Diversion and STP works in Bhagalpur under Hybrid annuity based PPP mode-Namami Gange Programme

Department of Water Resources, River Development & GRBihar
Revised Cost: ₹413 CrUtilization: 30.7%

Original Cost

₹413 Cr

Baseline estimate

On budget

Revised Cost

₹413 Cr

Latest approved cost

Expenditure

₹127 Cr

Spent to date

Utilization

30.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹286 Cr

Budget left

Budget Utilization

30.7%
0%25%50%75%100%

Spent

₹127 Cr

Remaining

₹286 Cr

Total

₹413 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/02/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code616600
SectorWaste & Water
MinistryDepartment of Water Resources, River Development & GR
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹413 Cr
Revised Cost₹413 Cr
Expenditure₹127 Cr
Original End Date06/02/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹413 Cr — no cost escalation recorded.

Expenditure stands at ₹127 Cr, which is 30.7% of the revised project cost.

Remaining budget: ₹286 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.

Interception and Diversion and STP works in Bhagalpur under Hybrid annuity based PPP mode-Namami Gange Programme is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Waste & Water sector. The original approved cost is ₹413.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Interception and Diversion and STP works in Bhagalpur under Hybrid annuity base"?
Interception and Diversion and STP works in Bhagalpur under Hybrid annuity based PPP mode-Namami Gange Programme is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Bihar. Original cost: ₹413 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹413 Cr has not been significantly revised. Expenditure: ₹127 Cr (30.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Interception and Diversion and STP works in Bhagalpur under is under the Department of Water Resources, River Development & GR in the Waste & Water sector. Project code: 616600. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Interception and Diversion and STP works in Bhagalpur under is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.