Integrated Multi Modal Logistics Hub at Nangal Chaudhary in Haryana - Other Trunk Infrastructure Development Phase 1
Original Cost
₹763 Cr
Baseline estimate
Revised Cost
₹763 Cr
Latest approved cost
Expenditure
₹430 Cr
Spent to date
Utilization
56.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹333 Cr
Budget left
Budget Utilization
56.4%Spent
₹430 Cr
Remaining
₹333 Cr
Total
₹763 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2023
Revised Completion
15/05/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹763 Cr — no cost escalation recorded.
Expenditure stands at ₹430 Cr, which is 56.4% of the revised project cost.
Remaining budget: ₹333 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Logistics Infrastructure. Ministry: Department for Promotion of Industry & Internal Trade.
Integrated Multi Modal Logistics Hub at Nangal Chaudhary in Haryana - Other Trunk Infrastructure Development Phase 1 is a centrally-funded infrastructure project under Department for Promotion of Industry & Internal Trade, in the Logistics Infrastructure sector. The original approved cost is ₹763.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Integrated Multi Modal Logistics Hub at Nangal Chaudhary in Haryana - Other Trun"?
- Integrated Multi Modal Logistics Hub at Nangal Chaudhary in Haryana - Other Trunk Infrastructure Development Phase 1 is a centrally-funded infrastructure project under the Department for Promotion of Industry & Internal Trade, tracked through the Investment Project Monitoring (IPM) system. Sector: Logistics Infrastructure. State: Haryana. Original cost: ₹763 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹763 Cr has not been significantly revised. Expenditure: ₹430 Cr (56.4% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Integrated Multi Modal Logistics Hub at Nangal Chaudhary in is under the Department for Promotion of Industry & Internal Trade in the Logistics Infrastructure sector. Project code: 707410. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Integrated Multi Modal Logistics Hub at Nangal Chaudhary in is one of several Bihar projects tracked under the Logistics Infrastructure sector on the IPM system.