IIT Gandhinagar - Development of Faculty/Staff Housing with Associated Facilities under Phase-2A
Original Cost
₹156 Cr
Baseline estimate
Revised Cost
₹156 Cr
Latest approved cost
Expenditure
₹130 Cr
Spent to date
Utilization
83.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹26 Cr
Budget left
Budget Utilization
83.6%Spent
₹130 Cr
Remaining
₹26 Cr
Total
₹156 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
31/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹156 Cr — no cost escalation recorded.
Expenditure stands at ₹130 Cr, which is 83.6% of the revised project cost.
Remaining budget: ₹26 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.
IIT Gandhinagar - Development of Faculty/Staff Housing with Associated Facilities under Phase-2A is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹156.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "IIT Gandhinagar - Development of Faculty/Staff Housing with Associated Facilitie"?
- IIT Gandhinagar - Development of Faculty/Staff Housing with Associated Facilities under Phase-2A is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Gujarat. Original cost: ₹156 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹156 Cr has not been significantly revised. Expenditure: ₹130 Cr (83.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- IIT Gandhinagar - Development of Faculty/Staff Housing with is under the Department of Higher Education in the Education sector. Project code: 858179. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. IIT Gandhinagar - Development of Faculty/Staff Housing with is one of several Bihar projects tracked under the Education sector on the IPM system.