CoalIPM · Central Project#616232

HINGULA II OC EXPN PH III 15 M

Ministry of CoalOdisha
Revised Cost: ₹1562 CrUtilization: 18.2%

Original Cost

₹1562 Cr

Baseline estimate

On budget

Revised Cost

₹1562 Cr

Latest approved cost

Expenditure

₹284 Cr

Spent to date

Utilization

18.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1278 Cr

Budget left

Budget Utilization

18.2%
0%25%50%75%100%

Spent

₹284 Cr

Remaining

₹1278 Cr

Total

₹1562 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2029

Revised Completion

Completed

Project Details

Project Code616232
SectorCoal
MinistryMinistry of Coal
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹1562 Cr
Revised Cost₹1562 Cr
Expenditure₹284 Cr
Original End Date31/03/2029
Revised DateN/A

Project Intelligence

Project is within original budget of ₹1562 Cr — no cost escalation recorded.

Expenditure stands at ₹284 Cr, which is 18.2% of the revised project cost.

Remaining budget: ₹1278 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

HINGULA II OC EXPN PH III 15 M is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹1562.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "HINGULA II OC EXPN PH III 15 M"?
HINGULA II OC EXPN PH III 15 M is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Odisha. Original cost: ₹1562 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1562 Cr has not been significantly revised. Expenditure: ₹284 Cr (18.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
HINGULA II OC EXPN PH III 15 M is under the Ministry of Coal in the Coal sector. Project code: 616232. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. HINGULA II OC EXPN PH III 15 M is one of several Bihar projects tracked under the Coal sector on the IPM system.