Original Cost
₹1562 Cr
Baseline estimate
Revised Cost
₹1562 Cr
Latest approved cost
Expenditure
₹279 Cr
Spent to date
Utilization
17.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1283 Cr
Budget left
Spent
₹279 Cr
Remaining
₹1283 Cr
Total
₹1562 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2029
Revised Completion
Completed
Project is within original budget of ₹1562 Cr — no cost escalation recorded.
Expenditure stands at ₹279 Cr, which is 17.9% of the revised project cost.
Remaining budget: ₹1283 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.