Original Cost
₹20.4K Cr
Baseline estimate
Revised Cost
₹20.4K Cr
Latest approved cost
Expenditure
₹1945 Cr
Spent to date
Utilization
9.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18.5K Cr
Budget left
Spent
₹1945 Cr
Remaining
₹18.5K Cr
Total
₹20.4K Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2030
Revised Completion
31/05/2030
Completed
Mega infrastructure project worth ₹20.4K Cr — among the largest central projects in Madhya Pradesh.
Project is within original budget of ₹20.4K Cr — no cost escalation recorded.
Expenditure stands at ₹1945 Cr, which is 9.5% of the revised project cost.
Remaining budget: ₹18.5K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.