Original Cost
₹393 Cr
Baseline estimate
Revised Cost
₹455 Cr
Latest approved cost
Expenditure
₹338 Cr
Spent to date
Utilization
74.2%
Of revised budget
Cost Status
+15.7%
+₹62 Cr increase
Remaining
₹117 Cr
Budget left
Spent
₹338 Cr
Remaining
₹117 Cr
Total
₹455 Cr
Original Cost
₹393 Cr
Revised Cost
₹455 Cr
Increase
+₹62 Cr
Escalation
+15.7%
Project Approved
Construction / Implementation
Original End Date
31/10/2023
Revised Completion
30/06/2026
Completed
Cost has increased by ₹62 Cr (15.7%) from the original estimate of ₹393 Cr.
Expenditure stands at ₹338 Cr, which is 74.2% of the revised project cost.
Remaining budget: ₹117 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.