EducationIPM · Central Project +15.7% overrun#602099

Establishment of Permanent campus Phase 1 of IIM Sirmaur

Department of Higher EducationHimachal Pradesh
Revised Cost: ₹455 CrUtilization: 74.8%Overrun: +₹62 Cr

Original Cost

₹393 Cr

Baseline estimate

+16% overrun

Revised Cost

₹455 Cr

Latest approved cost

Expenditure

₹340 Cr

Spent to date

Utilization

74.8%

Of revised budget

Escalated

Cost Status

+15.7%

+₹62 Cr increase

Remaining

₹115 Cr

Budget left

Budget Utilization

74.8%
0%25%50%75%100%

Spent

₹340 Cr

Remaining

₹115 Cr

Total

₹455 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹393 Cr

Revised Cost

₹455 Cr

Increase

+₹62 Cr

Escalation

+15.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/10/2023

Revised Completion

30/09/2026

Completed

Project Details

Project Code602099
SectorEducation
MinistryDepartment of Higher Education
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹393 Cr
Revised Cost₹455 Cr
Expenditure₹340 Cr
Original End Date31/10/2023
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹62 Cr (15.7%) from the original estimate of ₹393 Cr.

Expenditure stands at ₹340 Cr, which is 74.8% of the revised project cost.

Remaining budget: ₹115 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

Establishment of Permanent campus Phase 1 of IIM Sirmaur is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹393.00 Cr, later revised to ₹454.78 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Establishment of Permanent campus Phase 1 of IIM Sirmaur"?
Establishment of Permanent campus Phase 1 of IIM Sirmaur is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Himachal Pradesh. Original cost: ₹393 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹393 Cr and has been revised to ₹455 Cr — a cost overrun of +15.7%. Expenditure to date: ₹340 Cr (74.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Establishment of Permanent campus Phase 1 of IIM Sirmaur is under the Department of Higher Education in the Education sector. Project code: 602099. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Establishment of Permanent campus Phase 1 of IIM Sirmaur is one of several Bihar projects tracked under the Education sector on the IPM system.