Original Cost
₹276 Cr
Baseline estimate
Revised Cost
₹276 Cr
Latest approved cost
Expenditure
₹263 Cr
Spent to date
Utilization
95.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹13 Cr
Budget left
Spent
₹263 Cr
Remaining
₹13 Cr
Total
₹276 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2025
Revised Completion
Completed
Project is within original budget of ₹276 Cr — no cost escalation recorded.
Expenditure stands at ₹263 Cr, which is 95.4% of the revised project cost.
Remaining budget: ₹13 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.