CoalIPM · Central Project#400153

EPR ROHINI - KARKETTA OCP

Ministry of CoalJharkhand
Revised Cost: ₹996 CrUtilization: 8.6%

Original Cost

₹996 Cr

Baseline estimate

On budget

Revised Cost

₹996 Cr

Latest approved cost

Expenditure

₹85 Cr

Spent to date

Utilization

8.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹911 Cr

Budget left

Budget Utilization

8.6%
0%25%50%75%100%

Spent

₹85 Cr

Remaining

₹911 Cr

Total

₹996 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2028

Revised Completion

Completed

Project Details

Project Code400153
SectorCoal
MinistryMinistry of Coal
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹996 Cr
Revised Cost₹996 Cr
Expenditure₹85 Cr
Original End Date31/03/2028
Revised DateN/A

Project Intelligence

Project is within original budget of ₹996 Cr — no cost escalation recorded.

Expenditure stands at ₹85 Cr, which is 8.6% of the revised project cost.

Remaining budget: ₹911 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

EPR ROHINI - KARKETTA OCP is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹996.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "EPR ROHINI - KARKETTA OCP"?
EPR ROHINI - KARKETTA OCP is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Jharkhand. Original cost: ₹996 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹996 Cr has not been significantly revised. Expenditure: ₹85 Cr (8.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
EPR ROHINI - KARKETTA OCP is under the Ministry of Coal in the Coal sector. Project code: 400153. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. EPR ROHINI - KARKETTA OCP is one of several Bihar projects tracked under the Coal sector on the IPM system.