EPR PUNDI OCP
Original Cost
₹640 Cr
Baseline estimate
Revised Cost
₹640 Cr
Latest approved cost
Expenditure
₹15 Cr
Spent to date
Utilization
2.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹625 Cr
Budget left
Budget Utilization
2.3%Spent
₹15 Cr
Remaining
₹625 Cr
Total
₹640 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹640 Cr — no cost escalation recorded.
Expenditure stands at ₹15 Cr, which is 2.3% of the revised project cost.
Remaining budget: ₹625 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.
EPR PUNDI OCP is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹640.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "EPR PUNDI OCP"?
- EPR PUNDI OCP is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Jharkhand. Original cost: ₹640 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹640 Cr has not been significantly revised. Expenditure: ₹15 Cr (2.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- EPR PUNDI OCP is under the Ministry of Coal in the Coal sector. Project code: 400154. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. EPR PUNDI OCP is one of several Bihar projects tracked under the Coal sector on the IPM system.