Urban Public TransportIPM · Central Project#702632

DMRTS Phase - IV [3 Priority Corridors]

Ministry of Housing & Urban AffairsDelhi
Revised Cost: ₹24.9K CrUtilization: 86.9%

Original Cost

₹24.9K Cr

Baseline estimate

On budget

Revised Cost

₹24.9K Cr

Latest approved cost

Expenditure

₹21.7K Cr

Spent to date

Utilization

86.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹3263 Cr

Budget left

Budget Utilization

86.9%
0%25%50%75%100%

Spent

₹21.7K Cr

Remaining

₹3263 Cr

Total

₹24.9K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code702632
SectorUrban Public Transport
MinistryMinistry of Housing & Urban Affairs
StateDelhi
Data Month2026-08

Financial Summary

Original Cost₹24.9K Cr
Revised Cost₹24.9K Cr
Expenditure₹21.7K Cr
Original End Date31/03/2025
Revised Date31/12/2026

Project Intelligence

Mega infrastructure project worth ₹24.9K Cr — among the largest central projects in Delhi.

Project is within original budget of ₹24.9K Cr — no cost escalation recorded.

Expenditure stands at ₹21.7K Cr, which is 86.9% of the revised project cost.

Remaining budget: ₹3263 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.

DMRTS Phase - IV [3 Priority Corridors] is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹24949.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "DMRTS Phase - IV [3 Priority Corridors]"?
DMRTS Phase - IV [3 Priority Corridors] is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Delhi. Original cost: ₹24949 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹24949 Cr has not been significantly revised. Expenditure: ₹21686 Cr (86.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
DMRTS Phase - IV [3 Priority Corridors] is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 702632. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. DMRTS Phase - IV [3 Priority Corridors] is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.