Original Cost
₹31.9K Cr
Baseline estimate
Revised Cost
₹31.9K Cr
Latest approved cost
Expenditure
₹4714 Cr
Spent to date
Utilization
14.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹27.2K Cr
Budget left
Spent
₹4714 Cr
Remaining
₹27.2K Cr
Total
₹31.9K Cr
Project Approved
Construction / Implementation
Original End Date
26/02/2032
Revised Completion
26/02/2032
Completed
Mega infrastructure project worth ₹31.9K Cr — among the largest central projects in Arunachal Pradesh.
Project is within original budget of ₹31.9K Cr — no cost escalation recorded.
Expenditure stands at ₹4714 Cr, which is 14.8% of the revised project cost.
Remaining budget: ₹27.2K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.