Original Cost
₹373 Cr
Baseline estimate
Revised Cost
₹373 Cr
Latest approved cost
Expenditure
₹30 Cr
Spent to date
Utilization
8.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹343 Cr
Budget left
Spent
₹30 Cr
Remaining
₹343 Cr
Total
₹373 Cr
Project Approved
Construction / Implementation
Original End Date
31/10/2026
Revised Completion
Completed
Project is within original budget of ₹373 Cr — no cost escalation recorded.
Expenditure stands at ₹30 Cr, which is 8.1% of the revised project cost.
Remaining budget: ₹343 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.