Original Cost
₹6231 Cr
Baseline estimate
Revised Cost
₹6231 Cr
Latest approved cost
Expenditure
₹818 Cr
Spent to date
Utilization
13.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹5413 Cr
Budget left
Budget Utilization
13.1%Spent
₹818 Cr
Remaining
₹5413 Cr
Total
₹6231 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/01/2029
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹6231 Cr — no cost escalation recorded.
Expenditure stands at ₹818 Cr, which is 13.1% of the revised project cost.
Remaining budget: ₹5413 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.
Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor] is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹6231.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor]"?
- Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor] is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Haryana. Original cost: ₹6231 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹6231 Cr has not been significantly revised. Expenditure: ₹818 Cr (13.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor] is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 617206. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor] is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.