Original Cost
₹6231 Cr
Baseline estimate
Revised Cost
₹6231 Cr
Latest approved cost
Expenditure
₹558 Cr
Spent to date
Utilization
9.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹5673 Cr
Budget left
Spent
₹558 Cr
Remaining
₹5673 Cr
Total
₹6231 Cr
Project Approved
Construction / Implementation
Original End Date
02/01/2029
Revised Completion
Completed
Project is within original budget of ₹6231 Cr — no cost escalation recorded.
Expenditure stands at ₹558 Cr, which is 9.0% of the revised project cost.
Remaining budget: ₹5673 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.