Original Cost
₹11.1K Cr
Baseline estimate
Revised Cost
₹11.1K Cr
Latest approved cost
Expenditure
₹473 Cr
Spent to date
Utilization
4.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹10.7K Cr
Budget left
Spent
₹473 Cr
Remaining
₹10.7K Cr
Total
₹11.1K Cr
Project Approved
Construction / Implementation
Original End Date
31/01/2031
Revised Completion
31/05/2031
Completed
Mega infrastructure project worth ₹11.1K Cr — among the largest central projects in Odisha.
Project is within original budget of ₹11.1K Cr — no cost escalation recorded.
Expenditure stands at ₹473 Cr, which is 4.2% of the revised project cost.
Remaining budget: ₹10.7K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.