EducationIPM · Central Project +8.5% overrun#609736

Construction of Sikkim University Campus Phase-I Package-II at Yangang, South Sikkim

Department of Higher EducationSikkim
Revised Cost: ₹341 CrUtilization: 85.7%Overrun: +₹27 Cr

Original Cost

₹314 Cr

Baseline estimate

+9% overrun

Revised Cost

₹341 Cr

Latest approved cost

Expenditure

₹292 Cr

Spent to date

Utilization

85.7%

Of revised budget

Escalated

Cost Status

+8.5%

+₹27 Cr increase

Remaining

₹49 Cr

Budget left

Budget Utilization

85.7%
0%25%50%75%100%

Spent

₹292 Cr

Remaining

₹49 Cr

Total

₹341 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹314 Cr

Revised Cost

₹341 Cr

Increase

+₹27 Cr

Escalation

+8.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/01/2025

Revised Completion

31/10/2026

Completed

Project Details

Project Code609736
SectorEducation
MinistryDepartment of Higher Education
StateSikkim
Data Month2026-08

Financial Summary

Original Cost₹314 Cr
Revised Cost₹341 Cr
Expenditure₹292 Cr
Original End Date04/01/2025
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹27 Cr (8.5%) from the original estimate of ₹314 Cr.

Expenditure stands at ₹292 Cr, which is 85.7% of the revised project cost.

Remaining budget: ₹49 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

Construction of Sikkim University Campus Phase-I Package-II at Yangang, South Sikkim is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹314.00 Cr, later revised to ₹340.55 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Sikkim University Campus Phase-I Package-II at Yangang, South Si"?
Construction of Sikkim University Campus Phase-I Package-II at Yangang, South Sikkim is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Sikkim. Original cost: ₹314 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹314 Cr and has been revised to ₹341 Cr — a cost overrun of +8.5%. Expenditure to date: ₹292 Cr (85.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Sikkim University Campus Phase-I Package-II is under the Department of Higher Education in the Education sector. Project code: 609736. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Sikkim University Campus Phase-I Package-II is one of several Bihar projects tracked under the Education sector on the IPM system.