EducationIPM · Central Project#612876

Construction of Permanent Campus for NIT Mizoram at Lengpui, Aizawl

Department of Higher EducationMizoram
Revised Cost: ₹474 CrUtilization: 35.3%

Original Cost

₹474 Cr

Baseline estimate

On budget

Revised Cost

₹474 Cr

Latest approved cost

Expenditure

₹168 Cr

Spent to date

Utilization

35.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹307 Cr

Budget left

Budget Utilization

35.3%
0%25%50%75%100%

Spent

₹168 Cr

Remaining

₹307 Cr

Total

₹474 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2029

Revised Completion

31/03/2022

Completed

Project Details

Project Code612876
SectorEducation
MinistryDepartment of Higher Education
StateMizoram
Data Month2026-08

Financial Summary

Original Cost₹474 Cr
Revised Cost₹474 Cr
Expenditure₹168 Cr
Original End Date31/12/2029
Revised Date31/03/2022

Project Intelligence

Project is within original budget of ₹474 Cr — no cost escalation recorded.

Expenditure stands at ₹168 Cr, which is 35.3% of the revised project cost.

Remaining budget: ₹307 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

Construction of Permanent Campus for NIT Mizoram at Lengpui, Aizawl is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹474.00 Cr, later revised to ₹474.23 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Permanent Campus for NIT Mizoram at Lengpui, Aizawl"?
Construction of Permanent Campus for NIT Mizoram at Lengpui, Aizawl is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Mizoram. Original cost: ₹474 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹474 Cr has not been significantly revised. Expenditure: ₹168 Cr (35.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Permanent Campus for NIT Mizoram at Lengpui, is under the Department of Higher Education in the Education sector. Project code: 612876. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Permanent Campus for NIT Mizoram at Lengpui, is one of several Bihar projects tracked under the Education sector on the IPM system.