Original Cost
₹644 Cr
Baseline estimate
Revised Cost
₹644 Cr
Latest approved cost
Expenditure
₹162 Cr
Spent to date
Utilization
25.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹482 Cr
Budget left
Spent
₹162 Cr
Remaining
₹482 Cr
Total
₹644 Cr
Project Approved
Construction / Implementation
Original End Date
27/09/2027
Revised Completion
Completed
Project is within original budget of ₹644 Cr — no cost escalation recorded.
Expenditure stands at ₹162 Cr, which is 25.1% of the revised project cost.
Remaining budget: ₹482 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Construction . Ministry: Ministry of Housing & Urban Affairs.