Original Cost
₹861 Cr
Baseline estimate
Revised Cost
₹861 Cr
Latest approved cost
Expenditure
₹327 Cr
Spent to date
Utilization
38.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹534 Cr
Budget left
Spent
₹327 Cr
Remaining
₹534 Cr
Total
₹861 Cr
Project Approved
Construction / Implementation
Original End Date
21/06/2026
Revised Completion
30/11/2026
Completed
Project is within original budget of ₹861 Cr — no cost escalation recorded.
Expenditure stands at ₹327 Cr, which is 38.0% of the revised project cost.
Remaining budget: ₹534 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.