Original Cost
₹219 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹216 Cr
Spent to date
Utilization
78.5%
Of revised budget
Cost Status
+25.3%
+₹55 Cr increase
Remaining
₹59 Cr
Budget left
Spent
₹216 Cr
Remaining
₹59 Cr
Total
₹274 Cr
Original Cost
₹219 Cr
Revised Cost
₹274 Cr
Increase
+₹55 Cr
Escalation
+25.3%
Project Approved
Construction / Implementation
Original End Date
19/11/2024
Revised Completion
15/10/2025
Completed
Cost has increased by ₹55 Cr (25.3%) from the original estimate of ₹219 Cr.
Expenditure stands at ₹216 Cr, which is 78.5% of the revised project cost.
Remaining budget: ₹59 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.