Construction of New Terminal Building, Second Link Taxi Track, Apron Expansion, and associated works at Prayagraj Airport- On Design & Build Basis.
Original Cost
₹219 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹216 Cr
Spent to date
Utilization
78.5%
Of revised budget
Cost Status
+25.3%
+₹55 Cr increase
Remaining
₹59 Cr
Budget left
Budget Utilization
78.5%Spent
₹216 Cr
Remaining
₹59 Cr
Total
₹274 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹219 Cr
Revised Cost
₹274 Cr
Increase
+₹55 Cr
Escalation
+25.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/11/2024
Revised Completion
15/10/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹55 Cr (25.3%) from the original estimate of ₹219 Cr.
Expenditure stands at ₹216 Cr, which is 78.5% of the revised project cost.
Remaining budget: ₹59 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.
Construction of New Terminal Building, Second Link Taxi Track, Apron Expansion, and associated works at Prayagraj Airport- On Design & Build Basis. is a centrally-funded infrastructure project under Ministry of Civil Aviation, in the Aviation & Aviation Infrastructure sector. The original approved cost is ₹219.00 Cr, later revised to ₹274.38 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of New Terminal Building, Second Link Taxi Track, Apron Expansion, "?
- Construction of New Terminal Building, Second Link Taxi Track, Apron Expansion, and associated works at Prayagraj Airport- On Design & Build Basis. is a centrally-funded infrastructure project under the Ministry of Civil Aviation, tracked through the Investment Project Monitoring (IPM) system. Sector: Aviation & Aviation Infrastructure. State: Uttar Pradesh. Original cost: ₹219 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹219 Cr and has been revised to ₹274 Cr — a cost overrun of +25.3%. Expenditure to date: ₹216 Cr (78.5% of revised cost). Data as of 2025-11.
- QWhich ministry is responsible for this project?
- Construction of New Terminal Building, Second Link Taxi Trac is under the Ministry of Civil Aviation in the Aviation & Aviation Infrastructure sector. Project code: 612063. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Terminal Building, Second Link Taxi Trac is one of several Bihar projects tracked under the Aviation & Aviation Infrastructure sector on the IPM system.