Original Cost
₹480 Cr
Baseline estimate
Revised Cost
₹480 Cr
Latest approved cost
Expenditure
₹345 Cr
Spent to date
Utilization
72.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹135 Cr
Budget left
Spent
₹345 Cr
Remaining
₹135 Cr
Total
₹480 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
15/06/2026
Completed
Project is within original budget of ₹480 Cr — no cost escalation recorded.
Expenditure stands at ₹345 Cr, which is 72.0% of the revised project cost.
Remaining budget: ₹135 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.