Construction of New Integrated Terminal Building and associated works including apron to park 3 code E type of aircraft or 6 code C type of aircraft at Vijayawada Airport.
Original Cost
₹612 Cr
Baseline estimate
Revised Cost
₹824 Cr
Latest approved cost
Expenditure
₹601 Cr
Spent to date
Utilization
72.9%
Of revised budget
Cost Status
+34.7%
+₹212 Cr increase
Remaining
₹224 Cr
Budget left
Budget Utilization
72.9%Spent
₹601 Cr
Remaining
₹224 Cr
Total
₹824 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹612 Cr
Revised Cost
₹824 Cr
Increase
+₹212 Cr
Escalation
+34.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
04/09/2022
Revised Completion
10/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹212 Cr (34.7%) from the original estimate of ₹612 Cr.
Expenditure stands at ₹601 Cr, which is 72.9% of the revised project cost.
Remaining budget: ₹224 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.
Construction of New Integrated Terminal Building and associated works including apron to park 3 code E type of aircraft or 6 code C type of aircraft at Vijayawada Airport. is a centrally-funded infrastructure project under Ministry of Civil Aviation, in the Aviation & Aviation Infrastructure sector. The original approved cost is ₹612.00 Cr, later revised to ₹824.28 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of New Integrated Terminal Building and associated works including "?
- Construction of New Integrated Terminal Building and associated works including apron to park 3 code E type of aircraft or 6 code C type of aircraft at Vijayawada Airport. is a centrally-funded infrastructure project under the Ministry of Civil Aviation, tracked through the Investment Project Monitoring (IPM) system. Sector: Aviation & Aviation Infrastructure. State: Andhra Pradesh. Original cost: ₹612 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹612 Cr and has been revised to ₹824 Cr — a cost overrun of +34.7%. Expenditure to date: ₹601 Cr (72.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of New Integrated Terminal Building and associa is under the Ministry of Civil Aviation in the Aviation & Aviation Infrastructure sector. Project code: 701107. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Integrated Terminal Building and associa is one of several Bihar projects tracked under the Aviation & Aviation Infrastructure sector on the IPM system.