Original Cost
₹266 Cr
Baseline estimate
Revised Cost
₹266 Cr
Latest approved cost
Expenditure
₹143 Cr
Spent to date
Utilization
53.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹123 Cr
Budget left
Spent
₹143 Cr
Remaining
₹123 Cr
Total
₹266 Cr
Project Approved
Construction / Implementation
Original End Date
27/01/2026
Revised Completion
15/07/2026
Completed
Project is within original budget of ₹266 Cr — no cost escalation recorded.
Expenditure stands at ₹143 Cr, which is 53.6% of the revised project cost.
Remaining budget: ₹123 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.