Construction of 200 Bedded [Upgradable to 500 Bedded including 50 beds of SST] ESIC Hospital at Bibewadi, Pune
Original Cost
₹429 Cr
Baseline estimate
Revised Cost
₹429 Cr
Latest approved cost
Expenditure
₹342 Cr
Spent to date
Utilization
79.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹87 Cr
Budget left
Budget Utilization
79.7%Spent
₹342 Cr
Remaining
₹87 Cr
Total
₹429 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/09/2025
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹429 Cr — no cost escalation recorded.
Expenditure stands at ₹342 Cr, which is 79.7% of the revised project cost.
Remaining budget: ₹87 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Healthcare. Ministry: Ministry of Labour and Employment.
Construction of 200 Bedded [Upgradable to 500 Bedded including 50 beds of SST] ESIC Hospital at Bibewadi, Pune is a centrally-funded infrastructure project under Ministry of Labour and Employment, in the Healthcare sector. The original approved cost is ₹429.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 200 Bedded [Upgradable to 500 Bedded including 50 beds of SST] E"?
- Construction of 200 Bedded [Upgradable to 500 Bedded including 50 beds of SST] ESIC Hospital at Bibewadi, Pune is a centrally-funded infrastructure project under the Ministry of Labour and Employment, tracked through the Investment Project Monitoring (IPM) system. Sector: Healthcare. State: Maharashtra. Original cost: ₹429 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹429 Cr has not been significantly revised. Expenditure: ₹342 Cr (79.7% of cost). Data as of 2026-04.
- QWhich ministry is responsible for this project?
- Construction of 200 Bedded [Upgradable to 500 Bedded includi is under the Ministry of Labour and Employment in the Healthcare sector. Project code: 612188. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 200 Bedded [Upgradable to 500 Bedded includi is one of several Bihar projects tracked under the Healthcare sector on the IPM system.