HealthcareIPM · Central Project +8.2% overrun#612201

Construction of 200 bedded ESIC Hospital with 62 Nos Staff quarters , Beltola

Ministry of Labour and EmploymentAssam
Revised Cost: ₹155 CrUtilization: 84.1%Overrun: +₹12 Cr

Original Cost

₹143 Cr

Baseline estimate

+8% overrun

Revised Cost

₹155 Cr

Latest approved cost

Expenditure

₹130 Cr

Spent to date

Utilization

84.1%

Of revised budget

Escalated

Cost Status

+8.2%

+₹12 Cr increase

Remaining

₹25 Cr

Budget left

Budget Utilization

84.1%
0%25%50%75%100%

Spent

₹130 Cr

Remaining

₹25 Cr

Total

₹155 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹143 Cr

Revised Cost

₹155 Cr

Increase

+₹12 Cr

Escalation

+8.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/04/2025

Revised Completion

30/06/2026

Completed

Project Details

Project Code612201
SectorHealthcare
MinistryMinistry of Labour and Employment
StateAssam
Data Month2026-04

Financial Summary

Original Cost₹143 Cr
Revised Cost₹155 Cr
Expenditure₹130 Cr
Original End Date12/04/2025
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹12 Cr (8.2%) from the original estimate of ₹143 Cr.

Expenditure stands at ₹130 Cr, which is 84.1% of the revised project cost.

Remaining budget: ₹25 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Healthcare. Ministry: Ministry of Labour and Employment.

Construction of 200 bedded ESIC Hospital with 62 Nos Staff quarters , Beltola is a centrally-funded infrastructure project under Ministry of Labour and Employment, in the Healthcare sector. The original approved cost is ₹143.00 Cr, later revised to ₹154.75 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 200 bedded ESIC Hospital with 62 Nos Staff quarters , Beltola"?
Construction of 200 bedded ESIC Hospital with 62 Nos Staff quarters , Beltola is a centrally-funded infrastructure project under the Ministry of Labour and Employment, tracked through the Investment Project Monitoring (IPM) system. Sector: Healthcare. State: Assam. Original cost: ₹143 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹143 Cr and has been revised to ₹155 Cr — a cost overrun of +8.2%. Expenditure to date: ₹130 Cr (84.1% of revised cost). Data as of 2026-04.
QWhich ministry is responsible for this project?
Construction of 200 bedded ESIC Hospital with 62 Nos Staff q is under the Ministry of Labour and Employment in the Healthcare sector. Project code: 612201. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 200 bedded ESIC Hospital with 62 Nos Staff q is one of several Bihar projects tracked under the Healthcare sector on the IPM system.