Urban Public TransportIPM · Central Project#702665

Construction Bangalore Metro Rail Project Phase-2A & 2B

Ministry of Housing & Urban AffairsKarnataka
Revised Cost: ₹14.8K CrUtilization: 74.9%

Original Cost

₹14.8K Cr

Baseline estimate

On budget

Revised Cost

₹14.8K Cr

Latest approved cost

Expenditure

₹11.1K Cr

Spent to date

Utilization

74.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹3709 Cr

Budget left

Budget Utilization

74.9%
0%25%50%75%100%

Spent

₹11.1K Cr

Remaining

₹3709 Cr

Total

₹14.8K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2026

Revised Completion

30/06/2026

Completed

Project Details

Project Code702665
SectorUrban Public Transport
MinistryMinistry of Housing & Urban Affairs
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹14.8K Cr
Revised Cost₹14.8K Cr
Expenditure₹11.1K Cr
Original End Date30/06/2026
Revised Date30/06/2026

Project Intelligence

Mega infrastructure project worth ₹14.8K Cr — among the largest central projects in Karnataka.

Project is within original budget of ₹14.8K Cr — no cost escalation recorded.

Expenditure stands at ₹11.1K Cr, which is 74.9% of the revised project cost.

Remaining budget: ₹3709 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.

Construction Bangalore Metro Rail Project Phase-2A & 2B is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹14788.00 Cr, later revised to ₹14788.10 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction Bangalore Metro Rail Project Phase-2A & 2B"?
Construction Bangalore Metro Rail Project Phase-2A & 2B is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Karnataka. Original cost: ₹14788 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹14788 Cr has not been significantly revised. Expenditure: ₹11079 Cr (74.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction Bangalore Metro Rail Project Phase-2A & 2B is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 702665. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction Bangalore Metro Rail Project Phase-2A & 2B is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.