Original Cost
₹979 Cr
Baseline estimate
Revised Cost
₹979 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹979 Cr
Budget left
Spent
₹0 Cr
Remaining
₹979 Cr
Total
₹979 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2037
Revised Completion
Completed
Project is within original budget of ₹979 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹979 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.