Original Cost
₹514 Cr
Baseline estimate
Revised Cost
₹514 Cr
Latest approved cost
Expenditure
₹240 Cr
Spent to date
Utilization
46.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹274 Cr
Budget left
Spent
₹240 Cr
Remaining
₹274 Cr
Total
₹514 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
31/03/2028
Completed
Project is within original budget of ₹514 Cr — no cost escalation recorded.
Expenditure stands at ₹240 Cr, which is 46.7% of the revised project cost.
Remaining budget: ₹274 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.