Original Cost
₹611 Cr
Baseline estimate
Revised Cost
₹611 Cr
Latest approved cost
Expenditure
₹581 Cr
Spent to date
Utilization
95.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹30 Cr
Budget left
Spent
₹581 Cr
Remaining
₹30 Cr
Total
₹611 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹611 Cr — no cost escalation recorded.
Expenditure stands at ₹581 Cr, which is 95.0% of the revised project cost.
Remaining budget: ₹30 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.