Chennai Metro Rail Phase-II Development Project
Original Cost
₹63.2K Cr
Baseline estimate
Revised Cost
₹63.2K Cr
Latest approved cost
Expenditure
₹35.2K Cr
Spent to date
Utilization
55.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹28.0K Cr
Budget left
Budget Utilization
55.7%Spent
₹35.2K Cr
Remaining
₹28.0K Cr
Total
₹63.2K Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/08/2029
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Mega infrastructure project worth ₹63.2K Cr — among the largest central projects in Tamil Nadu.
Project is within original budget of ₹63.2K Cr — no cost escalation recorded.
Expenditure stands at ₹35.2K Cr, which is 55.7% of the revised project cost.
Remaining budget: ₹28.0K Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.
Chennai Metro Rail Phase-II Development Project is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹63246.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Chennai Metro Rail Phase-II Development Project"?
- Chennai Metro Rail Phase-II Development Project is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Tamil Nadu. Original cost: ₹63246 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹63246 Cr has not been significantly revised. Expenditure: ₹35228 Cr (55.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Chennai Metro Rail Phase-II Development Project is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 702668. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Chennai Metro Rail Phase-II Development Project is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.