Original Cost
₹974 Cr
Baseline estimate
Revised Cost
₹974 Cr
Latest approved cost
Expenditure
₹441 Cr
Spent to date
Utilization
45.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹533 Cr
Budget left
Spent
₹441 Cr
Remaining
₹533 Cr
Total
₹974 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2032
Revised Completion
Completed
Project is within original budget of ₹974 Cr — no cost escalation recorded.
Expenditure stands at ₹441 Cr, which is 45.3% of the revised project cost.
Remaining budget: ₹533 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.