[1320 MW]
Original Cost
₹10.4K Cr
Baseline estimate
Revised Cost
₹13.8K Cr
Latest approved cost
Expenditure
₹13.4K Cr
Spent to date
Utilization
97.2%
Of revised cost
Cost Overrun
+31.8%
+₹3318 Cr
Remaining
₹387 Cr
Budget left
Spent
₹13.4K Cr
Remaining
₹387 Cr
Total
₹13.8K Cr
97.2%
Utilized
Original Cost
₹10.4K Cr
Revised Cost
₹13.8K Cr
Increase
+₹3318 Cr
Escalation
+31.8%
Project Approved
Construction / Implementation
Original End Date
2024-01-08
Revised Completion
2026-05-30
Completed
This is a mega infrastructure project worth ₹13.8K Cr — among the largest central projects in Bihar.
Cost has increased by ₹3318 Cr (31.8%) from the original estimate of ₹10.4K Cr.
Expenditure stands at ₹13.4K Cr, which is 97.2% of the revised project cost.
Remaining budget: ₹387 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.