Electricity GenerationIPM · Central Project +31.8% overrun#602579

Buxar Thermal Power Project [1320 MW]

Ministry of PowerBihar
Revised Cost: ₹13.8K CrUtilization: 100.4%Overrun: +₹3318 Cr

Original Cost

₹10.4K Cr

Baseline estimate

+32% overrun

Revised Cost

₹13.8K Cr

Latest approved cost

Expenditure

₹13.8K Cr

Spent to date

Utilization

100.4%

Of revised budget

Escalated

Cost Status

+31.8%

+₹3318 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

100.4%
0%25%50%75%100%

Spent

₹13.8K Cr

Remaining

₹0 Cr

Total

₹13.8K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹10.4K Cr

Revised Cost

₹13.8K Cr

Increase

+₹3318 Cr

Escalation

+31.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/01/2024

Revised Completion

24/08/2026

Completed

Project Details

Project Code602579
SectorElectricity Generation
MinistryMinistry of Power
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹10.4K Cr
Revised Cost₹13.8K Cr
Expenditure₹13.8K Cr
Original End Date08/01/2024
Revised Date24/08/2026

Project Intelligence

Mega infrastructure project worth ₹13.8K Cr — among the largest central projects in Bihar.

Cost has increased by ₹3318 Cr (31.8%) from the original estimate of ₹10.4K Cr.

Expenditure stands at ₹13.8K Cr, which is 100.4% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Buxar Thermal Power Project [1320 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹10439.00 Cr, later revised to ₹13756.60 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Buxar Thermal Power Project [1320 MW]"?
Buxar Thermal Power Project [1320 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Bihar. Original cost: ₹10439 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹10439 Cr and has been revised to ₹13757 Cr — a cost overrun of +31.8%. Expenditure to date: ₹13814 Cr (100.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Buxar Thermal Power Project [1320 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602579. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Buxar Thermal Power Project [1320 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.