Original Cost
₹570 Cr
Baseline estimate
Revised Cost
₹570 Cr
Latest approved cost
Expenditure
₹89 Cr
Spent to date
Utilization
15.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹481 Cr
Budget left
Spent
₹89 Cr
Remaining
₹481 Cr
Total
₹570 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
31/03/2030
Completed
Project is within original budget of ₹570 Cr — no cost escalation recorded.
Expenditure stands at ₹89 Cr, which is 15.6% of the revised project cost.
Remaining budget: ₹481 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.