CoalIPM · Central Project#616231

BHUBANESWARI EXPN OCP 50 MTY

Ministry of CoalOdisha
Revised Cost: ₹5366 CrUtilization: 8.9%

Original Cost

₹5366 Cr

Baseline estimate

On budget

Revised Cost

₹5366 Cr

Latest approved cost

Expenditure

₹478 Cr

Spent to date

Utilization

8.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹4888 Cr

Budget left

Budget Utilization

8.9%
0%25%50%75%100%

Spent

₹478 Cr

Remaining

₹4888 Cr

Total

₹5366 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2033

Revised Completion

Completed

Project Details

Project Code616231
SectorCoal
MinistryMinistry of Coal
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹5366 Cr
Revised Cost₹5366 Cr
Expenditure₹478 Cr
Original End Date31/03/2033
Revised DateN/A

Project Intelligence

Project is within original budget of ₹5366 Cr — no cost escalation recorded.

Expenditure stands at ₹478 Cr, which is 8.9% of the revised project cost.

Remaining budget: ₹4888 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

BHUBANESWARI EXPN OCP 50 MTY is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹5366.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "BHUBANESWARI EXPN OCP 50 MTY"?
BHUBANESWARI EXPN OCP 50 MTY is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Odisha. Original cost: ₹5366 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹5366 Cr has not been significantly revised. Expenditure: ₹478 Cr (8.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
BHUBANESWARI EXPN OCP 50 MTY is under the Ministry of Coal in the Coal sector. Project code: 616231. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. BHUBANESWARI EXPN OCP 50 MTY is one of several Bihar projects tracked under the Coal sector on the IPM system.