CoalIPM · Central Project +101.0% overrun#400179

BHUBANESWARI EXPANSION OCP

Ministry of CoalOdisha
Revised Cost: ₹6322 CrUtilization: 19.8%Overrun: +₹3177 Cr

Original Cost

₹3145 Cr

Baseline estimate

+101% overrun

Revised Cost

₹6322 Cr

Latest approved cost

Expenditure

₹1251 Cr

Spent to date

Utilization

19.8%

Of revised budget

Escalated

Cost Status

+101.0%

+₹3177 Cr increase

Remaining

₹5071 Cr

Budget left

Budget Utilization

19.8%
0%25%50%75%100%

Spent

₹1251 Cr

Remaining

₹5071 Cr

Total

₹6322 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹3145 Cr

Revised Cost

₹6322 Cr

Increase

+₹3177 Cr

Escalation

+101.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2031

Revised Completion

Completed

Project Details

Project Code400179
SectorCoal
MinistryMinistry of Coal
StateOdisha
Data Month2025-07

Financial Summary

Original Cost₹3145 Cr
Revised Cost₹6322 Cr
Expenditure₹1251 Cr
Original End Date31/03/2031
Revised DateN/A

Project Intelligence

Cost has increased by ₹3177 Cr (101.0%) from the original estimate of ₹3145 Cr.

Expenditure stands at ₹1251 Cr, which is 19.8% of the revised project cost.

Remaining budget: ₹5071 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

BHUBANESWARI EXPANSION OCP is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹3145.00 Cr, later revised to ₹6321.73 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "BHUBANESWARI EXPANSION OCP"?
BHUBANESWARI EXPANSION OCP is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Odisha. Original cost: ₹3145 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹3145 Cr and has been revised to ₹6322 Cr — a cost overrun of +101%. Expenditure to date: ₹1251 Cr (19.8% of revised cost). Data as of 2025-07.
QWhich ministry is responsible for this project?
BHUBANESWARI EXPANSION OCP is under the Ministry of Coal in the Coal sector. Project code: 400179. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. BHUBANESWARI EXPANSION OCP is one of several Bihar projects tracked under the Coal sector on the IPM system.