Original Cost
₹316 Cr
Baseline estimate
Revised Cost
₹316 Cr
Latest approved cost
Expenditure
₹192 Cr
Spent to date
Utilization
60.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹125 Cr
Budget left
Spent
₹192 Cr
Remaining
₹125 Cr
Total
₹316 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
Completed
Project is within original budget of ₹316 Cr — no cost escalation recorded.
Expenditure stands at ₹192 Cr, which is 60.6% of the revised project cost.
Remaining budget: ₹125 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.