Original Cost
₹399 Cr
Baseline estimate
Revised Cost
₹399 Cr
Latest approved cost
Expenditure
₹101 Cr
Spent to date
Utilization
25.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹298 Cr
Budget left
Spent
₹101 Cr
Remaining
₹298 Cr
Total
₹399 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
Completed
Project is within original budget of ₹399 Cr — no cost escalation recorded.
Expenditure stands at ₹101 Cr, which is 25.2% of the revised project cost.
Remaining budget: ₹298 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.